20150224

Construction - week 2

Hard to believe a whole week has gone by . . . and the work continues . . .





Monday . . . electrical removed most of the old lines and boxes.  Put new circuits in to power those areas we aren't working in, but were affected by the power out in the kitchen.



All the homeruns hanging . . . while there was still a floor to work on

 Tuesday - plumbers got busy
 and the floor got removed

 and we found some nice slabs of rock . . .



Wednesday . . . plumbing continues and the joists are going in . . .




Looks the same but it works now . . .
and surprise, surprise, we found a well . . . 


Joists lined up and ready for a floor . . .



and thursday . . . part of the floor is in and the bones are in the making . . .


interior walls around the powder room and pantry . . .

And friday . . . window day . . .


windows removed . . . actually